For the first two weeks of the Processor Design Project (PDP), edition 2025, you are expected to perform the following tasks:

Task 1:⁠ ⁠Make sure that the basic RISCY core, the LLVM toolchain, and the AES software implementation are all working. Please note that at this first stage, no modifications to the RISCY core or the LLVM compiler are expected. Your job is to synthesize the provided RISCY core including the peripherals and other IPs using Vivado, load the generated bitstream into the FPGA board, compile the base AES software implementation and run it on the RISCY core that was already loaded on the FPGA board. A detailed manual on how to do all of this is provided. Now you are ready to really start the PDP project.

Since in the second phase of the project (starting in week 3) you will be extending this basis RISCY system with the two standard AES encryption instructions AND the loop-unrolling pass for the AES inner round instruction, some additional reading and thinking is expected in the first phase. Moreover, you will be also evaluating and reporting the quantitative improvements provided by your RISCY_AES system against the baseline RISCY + AES in software. In addition, you are expected to propose, implement and evaluate additional system improvement(s). The next tasks will help you with the preparation for the above.

Task 2: Perform a literature review of what has been already done on RISCV, AES hardware implementations and AES specific compiler optimizations. ⁠⁠This will familiarise you with the work already done and reported in order to then better decide on the extensions/improvements your team will commit to. Your findings will be described in the background section of your first report (due at the end of week 2). This task will also help you identify the state-of-the-art to compare against your final project results.

Task 3:⁠ ⁠Analyse the base system bottlenecks (choose your method, e.g., analytical, static dynamic, etc), forecast how the AES instruction extensions and loop unrolling will impact those and make initial plans (hypothesis) how to improve the extended system. The intended improvements can be any of these but not limited to:

  • lowest execution latency;
  • highest throughput;
  • minimal area utilisation;
  • minimal memory footprint / register pressure;
  • (any other quantitative improvement you group commits to work on during the final phase of the project).

Note: Precise energy simulation and measurements can be quite challenging on the FPGA platform used. Please consult the lab sessions team in case you have questions about this.

Task 4: Write your intermediate report incorporating the following. Your hypothesis for RISCY_AES+LLVM extensions, additional improvements and plans on how to implement, debug and validate those. Create a detailed project plan for the second phase (weeks 3 to 8) with internal tasks (do not forget to assign team members to those) and built-in milestones to help with monitor your progress. Please mind that the project has hard deadline at the end of week 8! You are free to decide on the specific internal tasks, their distribution and interdependencies. Please mind that this is a complex project and you are expected to work together as a team. You have to also describe what you will compare against (the state-of-the-art in your background section) and how you plan to obtain the quantitative results needed to support your claims. Do not forget to mention explicitly who contributed what to the sections and activities described in the report.

Deliver your report at the end of week 2 and start with implementing and integrating the AES encryption instructions (aes32esi and aes32esmi). Once this is done, use the LLVM built-in loop-unrolling pass for the AES inner round instruction (aes32esmi). One week later (end of week 3) you will receive detailed feedback in order to improve your original plans for the additional improvements as described in your intermediate report.